Terminal Design Specifications

 

TERMINAL CONFIGURATION & DESIGN SPECIFICATIONS

LNG Storage Capacity 4 - 180,000 cubic meters (m3) full-containment storage tanks.
Regasification Capacity 2.0 Billion Cubic Feet (bcf) per day.
Pipeline Interconnection Offshore, subsea natural gas pipeline, connects to interstate pipeline grid.
Power Facilities Island power supply fueled by clean, natural gas engines.
Waste heat from power facilities used in the LNG process.
Marine Facilities Two protected docking and unloading facilities for LNG tankers
with capacities of 70,000 to more than 250,000 m3.
Additional small craft docking for safety and supply vessels.
Vaporization Facilities Ambient air vaporization equipment to convert LNG into natural
gas without using seawater.
Other Facilities Self-contained fire, security and communication facility
in accordance to U.S Coast Guard regulations.
- BACK TO TOP -